    SPECIFICATION OF RBS ENGINEERING WORK

    PROCESS

    Abstract

    This document describes the RBS engineer work activity and procedure. It is

    applied to all DEC/NJ RBS engineers.

1 INTERFACE

    1.1 INPUT

    Content From

    Material list PM

    Site list and configuration PM

    Assignment Specification PM 1.2 OUTPUT

     Content To

    Site investigation report PM or RND

    Installation Document Customer & PM

    C-module Document TA & customer 2 MAIN ACTIVITIES

    ; Material list verification

    ; Site investigation preparation

    ; Site investigation

    ; A-pack production

    ; Installation Document production

    ; Installation Document updating

    Ericssonwide Internal 2 (6) PROCESS DESCRIPTION Prepared (also subject responsible if other) No.

    DEC/NJ/E Si-ma Mingjin DEC/NJ/E-2002:012 Uen Approved Checked Date Rev Reference

     DEC/NJ/EC (Wang Shanjun) 2004-06-29 C

    2.1 MATERIAL LIST VERIFICATION

    Objective

    To help dimension department to check the material list. Activity

    Check the site list & configuration and material list to make sure the product number and quantity, if have something wrong, feedback the information to PM and dimension engineer.

    Reference and Tools

; General Installation Manual (EN/LZB 119 2693/1 Uen)

; Ordering information (131 62-HRB 105 01 Uen)

    ; Installation Engineering Manual (EN/LZB 119 1582/1 Uen)

; PRIM, GASK, etc.

    2.2 SITE INVESTIGATION PREPARATION

    Document Preparation

    ; Study site list & configuration, and make a site list that needs to be

    surveyed; it should contain the site name, site ID, site type, site

    configuration, etc.

    ; For expansion sites, print all old floor plan drawings, cableway drawings

    and antenna arrangement drawings.

    Tools Preparation

    Prepare the tools for survey, it contains: GPS, Measuring tape, Compass, Binoculars, Camera, Scale ruler, Pen, Pencil.

    Measurement

    ; Site list that needs to be surveyed

    ; For expansion sites, three drawings should be printed

    ; Tools are ready

    Ericssonwide Internal 3 (6) PROCESS DESCRIPTION Prepared (also subject responsible if other) No.

    DEC/NJ/E Si-ma Mingjin DEC/NJ/E-2002:012 Uen Approved Checked Date Rev Reference

     DEC/NJ/EC (Wang Shanjun) 2004-06-29 C

    2.3 SITE INVESTIGATION

Activity

    1. Check the site list & configuration with customer or design institute, and

    update the site list & configuration

    2. Site Investigation

    ; Get coordinates (Latitude, Longitude)

    ; Give customer suggestion for power and earthing requirements.

    ; Make a sketch of floor plan and cable way indoor

    ; Make a sketch of antenna arrangement and cable way outdoor

    ; Indicate the magnetic north on the sketch

    ; Take photos indoor and outdoor

    ; Fill Investigation record and take some useful notes

    ; Confirm the draft design (floor plan drawing, cableway drawing,

    antenna arrangement drawing) with customer and get customer

    signature

3. Make site investigation report according to a standard investigation form,

    then report to PM and RND engineer. The report contents includes:

    ; Site name

    ; Site ID

    ; Site type

    ; Site configuration

    ; Power type

    ; Transmission

    ; Coordinates (Latitude, Longitude)

    ; Antenna height, Antenna direction, Antenna type

    ; Feeder length

    ; Installation manner (only for RBS1127 site)

    ; Optical cable length (only for RBS 1127 site)

    Ericssonwide Internal 4 (6) PROCESS DESCRIPTION Prepared (also subject responsible if other) No.

    DEC/NJ/E Si-ma Mingjin DEC/NJ/E-2002:012 Uen Approved Checked Date Rev Reference

     DEC/NJ/EC (Wang Shanjun) 2004-06-29 C

References

    ; General Installation Manual (EN/LZB 119 2693/1 Uen) ; Installation engineering manual (EN/LZB 119 1582/1 Uen) ; Site Requirement and Planning Manual (EN/LZT 123 2678 Uen) ; Antenna Guideline (155 19-COA 109 117 Uen) Measurement

    ; Site investigation report

    ; Investigation record

    ; Draft design (floor plan drawing, cableway drawing, antenna arrangement

    drawing)

    2.4 A-PACK PRODUCTION

    Objective

    Order installation material for Base Station installation Input

    ; Material list

    ; Updated Site list & configuration table

    ; Site investigation report

    Activity

    1. Get the material list “read” access right in BRIS from Dimension

    Department.

    2. Make material list and send it to BRIS

    Tools

    BRIS

    Measurement

    A-Pack production release in BRIS

    Ericssonwide Internal 5 (6) PROCESS DESCRIPTION Prepared (also subject responsible if other) No.

    DEC/NJ/E Si-ma Mingjin DEC/NJ/E-2002:012 Uen Approved Checked Date Rev Reference

     DEC/NJ/EC (Wang Shanjun) 2004-06-29 C

    2.5 INSTALLATION DOCUMENT PRODUCTION Objective

    Provide site installation documents to installation engineer

    Input

    ; Material list

    ; Updated site list & configuration table

    ; Site investigation report

; Draft design

    Activity

    1. Drawing design

    ; Make floor plan drawings

    ; Make cable way drawing

    ; Make antenna arrangement drawing 2. Make cable diagrams

    3. Material specification 4. Make label and print out 5. Assemble installation documents

     Including:

    ; List of documents

    ; Site documents

    ; Specification list

    ; Cabling

    ; Alarms

    ; Test records

    ; Check list

    ; Label

    Ericssonwide Internal 6 (6) PROCESS DESCRIPTION Prepared (also subject responsible if other) No.

    DEC/NJ/E Si-ma Mingjin DEC/NJ/E-2002:012 Uen Approved Checked Date Rev Reference

     DEC/NJ/EC (Wang Shanjun) 2004-06-29 C

6. Make quality check list and send installation documents to an experienced

    engineer for quality check

    7. Correct if any mistake

    8. Make delivery list and send to TA

Reference

    ; General Installation Manual (EN/LZB 119 2693/1 Uen) ; Installation engineering manual (EN/LZB 119 1582/1 Uen) ; Site Requirement and Planning Manual (EN/LZT 123 2678 Uen) ; Antenna Guideline (155 19-COA 109 117 Uen)

Tools

    AUTOCAD14.0, Word, Excel, etc.

Measurement

    Installation documents are ready to hand over to TA

    2.6 INSTALLATION DOCUMENT UPDATING

    Objective

    Update feedback installation documents and keep as record Input

    Installation documents feedback from PM

    Activity

    1. Updating installation documents to C-Module according to the red marks

    2. Hand over the C-module to TA, one copy of the C-Module will be sent to

    customer if requested by PM, electronic file to TA for storage Output

    ; C-module document on group driver and paper