SPECIFICATIONSPEC

D30 PILING

    SPECIFICATION FOR

    PILING

    SECTION D30

    Revision Date Issue Authorised By

Approved for Issue S Williams

    Date 21 Dec 2007

    Author SW Bettws School Newport JOB No SC00940 21 Dec 07 Rev -

     Page 1 of 8 clarkebond

D30 PILING

    To be read with Preliminaries/ General conditions.

010 INFORMATION TO BE PROVIDED WITH TENDER

    Submit:

    - Information listed in SPERW, table 1.1.

    - Other Information: [

    o Proposals for reducing noise and vibration from piling operations.

    o Typical pile record sheets and confirmation that a complete record sheet will be

    produced for every pile.

    o Where piles are contractor designed (clause 210) insert, e g. Pile design basis

    and calculations.

    o Proposals for ensuring possible lateral loads from ground influenced by trees will

    not damage the piles.__]

    SERVICES AFFECTED BY PILING

020 B SERVICES REGULATIONS

    Any work carried out to or which affects new or existing services must be in accordance with

    the byelaws or regulations of the relevant statutory authority.

022 B LOCATION OF SERVICES

    Locate and mark the positions of services affected by the work. Arrange with the appropriate

    authorities for the location and marking of the positions of mains services.

024 B DISCONNECTION OF SERVICES

    Before starting piling arrange with the appropriate authorities for the disconnection of

    services and removal of fittings and equipment.

    There are existing services under the proposed building. It is anticipated diversion works will

    be carried out by the main Contractor. The specialist piling subcontractor must satisfy

    themselves that services have been removed.

030 B DISCONNECTION OF DRAINS

    Locate and disconnect all disused drain connections. Seal within the site to approval.

    There are no known sewers crossing the site. As the site is currently a playing field some

    land drains may be encountered.

036 B SERVICES WHICH ARE TO REMAIN

    Notify the CA and service authority or owner of any damage. Make all arrangements for

    repair to the satisfaction of the CA and service authority or owner. Bear any costs arising.

    GENERAL

110 PILING SPECIFICATION

    Standard: Comply with the current edition of the „Specification for Piling and Embedded

    Retaining Walls‟ (SPERW).

    Substitution of British Standard for SPERW requirements: Submit proposals for approval if

    relevant.

    References to Engineer in SPERW: For the purpose of this contract, interpret such

    references as being the person named in section A10 as administering the contract on behalf

    of the Employer.

112 B PILING MAT

    The design of the piling mat is the responsibility of the Contractor.

    - Piling platform level: Proposed level to be 12.6m AOD. (400mm below FFL)

    - Design and construction details: Submit.

    Timing: 21 days before start of construction of piling mat.

Author SW Bettws School Newport JOB No SC00940

    21 Dec 07 Rev -

     Page 2 of 8 clarkebond

    D30 PILING

    120 ERRATA AND ADDENDA TO SPERW

    Table 1.2: In the penultimate line substitute 4.10 for 4.8.

    Clause 2.9.6(c): Substitute 20 for 21. Other requirements:

    Welding of tube piles to SPERW, section 5 as welding requirements in section 6.

    130 PILES

    Standard: To SPERW, sections 2-6 and 20, as appropriate to the pile type.

    Permitted types: Contractors Choice

    Particular specification: Submit proposals to cover the SPERW requirements listed under this

    heading for the chosen pile type. Other requirements: Noise and Dust must not impact on the users of the adjacent school.

     Selected piles will need to resist lateral movement of ground where influenced by trees.

     Attention is drawn to the lateral and moment loads that will be applied to the piles.

    140 PRECAST CONCRETE PILES

    Standard: To SPERW, section 2.

    Type: Submit proposals.

    Manufacturer: Submit proposals.

    - Product reference: Submit proposals.

    Joints: Submit proposals.

    Shoes: Submit proposals.

    Pile group designation: Submit proposals.

    - Section size: Submit proposals.

    - Length: Submit proposals.

    - Other requirements: See clause 130.

    150 STEEL BEARING PILES

    Standard: To SPERW, section 6.

    Manufacturer: Submit proposals.

    - Product type: Submit proposals.

    Steel designation: Submit proposals.

    Joints: Submit proposals.

    Head reinforcement: Submit proposals.

    Shoes/ toe reinforcement: Submit proposals.

    Pile group designation: Submit proposals.

    - Section size: Submit proposals.

    - Length: Submit proposals.

    - Other requirements: See clause 130.

    160 DRIVEN CAST-IN-PLACE PILES WITH PERMANENT CASING

    Standard: To SPERW, sections 5 and 20. Casing:

    - Type: Submit proposals.

    - Material strength class/ grade: Submit proposals.

    - Wall thickness: Submit proposals.

    - Section length (minimum): Submit proposals.

    - Joints: Submit proposals.

    - Shoes/ toe reinforcement: Submit proposals.

    Filling material: Submit proposals.

    Pile group designation: Submit proposals.

    - Diameter: Submit proposals.

    - Length: Submit proposals.

    - Reinforcement:

    Quality: Submit proposals.

    Extent: Submit proposals.

    Author SW Bettws School Newport JOB No SC00940

    21 Dec 07 Rev -

     Page 3 of 8 clarkebond

D30 PILING

    - Other requirements: See clause 130.

170 BORED CAST-IN-PLACE PILES

    Standard: To SPERW, sections 3 and 20.

    Filling material: Submit proposals.

    Pile group designation: Submit proposals.

    - Diameter: Submit proposals.

    - Length: Submit proposals.

    - Reinforcement:

    Quality: Submit proposals.

    Extent: Submit proposals.

    - Other requirements: See clause 130.

    180 FLIGHT AUGERED CAST-IN-PLACE PILES

    Standard: To SPERW, sections 4 and 20.

    Filling:

    - Material: Submit proposals.

    - Placing: Inject through hollow stem of auger.

    Pile group designation: Submit proposals.

    - Diameter: Submit proposals.

    - Length: Submit proposals.

    - Reinforcement:

    Quality: Submit proposals.

    Extent: Submit proposals.

    - Other requirements: See clause 130.

    SYSTEM PERFORMANCE

210 CONTRACTOR DESIGN

    Standard: To BS 8004.

    Requirement: Complete design of piles and construct in accordance with SPERW, clause 1.4

    option 1.

    Pile layout: The pile layout will be determined by Clarkebond. Generally there will be single

    piles under each column plus additional isolated piles under ground slabs.

    Site investigation: Confirm as adequate or propose further investigation as considered

    necessary.

230 GROUND INVESTIGATION

    Report: Available. A project specific site investigation has been carried out by Terrafirma. A

    draft report has been produced in October 2007 and is available.

    Datum for borehole logs: Existing ground levels. A topographical survey is available.

250 PERFORMANCE CRITERIA FOR STRUCTURE TO BE SUPPORTED ON THE PILES

    Permitted settlement at working load (maximum): 10mm

    260 SPECIFIED WORKING LOAD FOR PILES

    Pile group designation: Typical piles circa 250mm square or 250mm diameter.

    - Load magnitude:

    - Load case 1; SWL 550kN F.O.S = 2.5

    - Load case 2; Safe Working Moment 8.75kNm. Safe Horizontal Load 2.5kN. FOS = 2.0

    - Load case 3; Safe Working Moment 8.75kNm. Safe Horizontal Load 20kN. Safe axial load

    = 135kN to 550kN FOS = 2.0

    Pile group designation: Enhanced piles circa 300mm square or 300mm diameter.

    - Load magnitude:

    - Load case 1; SWL 700kN F.O.S = 2.5

    - Load case 2; Safe Working Moment 8.75kNm. Safe Horizontal Load 2.5kN. FOS = 2.0 Author SW Bettws School Newport JOB No SC00940 21 Dec 07 Rev -

     Page 4 of 8 clarkebond

D30 PILING

    - Load case 3; Safe Working Moment 8.75kNm. Safe Horizontal Load 20kN. Safe axial load

    = 135kN to 550kN FOS = 2.0

270 PILE TYPES AND NUMBERS

    Exact pile numbers will be shown on the drawings when available. It is anticipated pile

    numbers will be as follows:

    Number of typical 550kNin total. 276

    Number subject to lateral loading from ground movement. 45

    Number with an increased load of 700kN. 20

     Total 341

    280 PERFORMANCE CRITERIA FOR PILES UNDER LOAD TEST

    Pile group designation: 500kN SWL

    - Dimensions: As for working piles.

    Pile reference for test piles:

    - Preliminary test: Not required.

    - Proof test: 2 piles. Location to be agreed

    Test criteria:

    - Specified working load (SWL): 500kN

    - Design verification load (DVL): 500kN

    - Load factor: 2.5

    - Permitted settlement at DVL: 8mm

    - Permitted settlement at DVL + ? SWL: 12mm

290 BASIS FOR SETTING OUT

    Site datum: AOD

    Site grid: As drawings

300 COMMENCING SURFACE

    Level: 12.6m AOD

310 PILE LENGTH - PENETRATION

    Pile group designation: All

    Pile cut off level: As drawings. Varies between 12.4m AOD and 11.5m AOD

    - Other requirements: Define set criteria prior to installing piles and maintain proof of

    achieving set.

    330 DRIVING RESISTANCE, DYNAMIC EVALUATION AND SET

    Requirement: Drive pile until minimum specified pile penetration is achieved and, until

    following are achieved:

    - Energy imparted to pile: Submit proposals.

    Set: Submit proposals.

    Energy rating of hammer: Provide evidence that energy imparted to pile by proposed

    hammer will be satisfactory and that hammer has been maintained and checked in

    accordance with hammer manufacturer‟s instructions.

    Other requirements: Submit proposals.

    PRODUCTS

410 HEAD PREPARATION

    Minimum requirement for strengthening pile head prior to driving: Submit proposals.

    Amendment to design: Submit proposals for changes if found necessary to prevent damage

    to pile heads.

420 PILE SHOES OR TOE REINFORCEMENT

    Requirement: Submit proposals.

    Type: Submit proposals.

    Author SW Bettws School Newport JOB No SC00940 21 Dec 07 Rev -

     Page 5 of 8 clarkebond

D30 PILING

    - Material: Submit proposals.

    Details: Submit proposals.

430 MARKING PRECAST CONCRETE PILES

    Clearly mark each pile with:

    - Date of casting.

    - Unique reference number.

    - Principal dimensions.

    - Other requirements None

440 PERMANENT CASING

    Reasons for use: To resist ground movement due to the influence of trees.

    Casing:

    - Material: Steel anticipated. Submit proposals.

    - Diameter: Submit proposals.

    - Thickness: Submit proposals.

    - Length: Full pile length.

    - Coating: Submit proposals.

    Method of installation: Submit proposals.

    Backfilling of annulus:

    - Between casing and ground: Submit proposals.

    - Between casing and pile: Submit proposals.

470 CONCRETE GENERALLY

    Standards: To BS 8500-2 and SPERW, section 20.

    Exchange of information: Provide concrete producer with information required by BS 8500-1,

    clauses 4 and 5.

530 REINFORCEMENT GENERALLY

    Steel reinforcement: To BS 4449.

    - Type/ Grade: Submit proposals.

    Cutting and bending: To BS 8666.

    Supplier: Firm holding a valid certificate of approval issued under a product certification

    scheme operated by a third party certification body with appropriate Category 2 accreditation

    from the United Kingdom Accreditation Service (UKAS).

540 COVER TO REINFORCEMENT

    Cover (nominal): 40mm minimum.

    Method of ensuring correct cover: Submit details.

550 LAPS IN REINFORCEMENT

    Length (minimum): 40 x bar diameter.

    EXECUTION

610 METHOD STATEMENT

    Requirement: Submit proposed method of installation to achieve the design parameters

    including:

    - Details of equipment

    - Programme showing sequence and resources

    - Confirmation that performance requirements for load and settlement will be achieved.

630 PRELIMINARY PILES

    Locations: Contractors choice. Submit proposals.

    - Diameter: Submit proposals.

    - Allowable pile capacity: Submit proposals.

    Author SW Bettws School Newport JOB No SC00940 21 Dec 07 Rev -

     Page 6 of 8 clarkebond

D30 PILING

635 TRIAL DRIVES

    Locations: Contractors choice. Submit proposals.

    Timing: Before installation of contract piles.

640 TRIAL BORES

    Locations: Contractors choice. Submit proposals.

    Timing: Before installation of contract piles.

645 UPLIFT AND LATERAL DISPLACEMENT TRIALS

    Uplift trial: Contractors choice. Submit proposals.

    Lateral displacement trial: Contractors choice. Submit proposals.

650 PERFORMANCE OF WORKING PILES

    Substandard performance: Give notice if the performance of any pile will be less than that of

    a similar pile whose test behaviour has been accepted.

685 EXCAVATED MATERIAL

    Disposal: By main contractor.

687 B EXCAVATED MATERIAL CLASSIFIED FOR RE-USE ON SITE

    All excavated material designated for re-use on site, considered contaminated at a location

    remote from the original point of excavation must have approval from the Environment

    Agency for use as filling. Excavated materials must not be mixed or blended for re-use on

    site without the agreement of the Environment Agency

    Transportation of excavated materials shall be in accordance with:

    ; The Environmental Protection Act 1990 (Duty of Care) as laid down by the Environment

    Agency

    ; Planning conditions

    ; Health and Safety Executive (HS(G)66) - “Protection of workers and the general public during

    the development of contaminated land”.

    A copy of all records of agreements with the Environment Agency and others shall be

    available for inspection by the CA and incorporated into the Site File in accordance with the

    requirements of the Construction (Design and Management) Regulations 1994.

690 A DISPOSAL OF PILE HEADS

    Cutting down and disposal: Contractor‟s responsibility.

    Use of hand held percussive tools: Eliminate whenever possible or minimise.

735 METHOD OF TESTING CONCRETE WORKABILITY

    Test: To BS 8500-1, Annex B.

    Workability: To SPERW, table 3.1.

    Test method:

    - Slump testing: For mixes with workability type A as SPERW, table 3.1.

    - Flow testing: For higher workability mixes, unless agreed otherwise.

740 COMPRESSION TESTING OF CONCRETE

    Requirement: In addition to any sampling and testing carried out by the concrete supplier,

    and unless otherwise agreed, sample concrete on site and test.

    Sampling rate: 1 sample of 4 cubes per 12 cubic meters of concrete or 1 sample per day.

    Whichever is most.

755 PREPARATION OF PILE HEADS FOR INTEGRITY TESTING

    Preparation: To suit test method.

    Inconsistencies: Submit report on inconsistencies which could inhibit execution or

    interpretation of test.

760 INTEGRITY TESTING - GENERAL

    Author SW Bettws School Newport JOB No SC00940

    21 Dec 07 Rev -

     Page 7 of 8 clarkebond

D30 PILING

    Method: Contractors choice. Submit proposals.

    - Satisfactory evidence in support of proposals: Submit.

    Period between casting and testing (minimum): 15 days.

    Piles to be tested:

    - Pile group designation: All.

    - Type: All.

    - Number: All.

    - Locations: All.

    Programme: TBA

    775 PERIODS FOR SUBMISSION OF INTEGRITY TEST RESULTS

    Initial test results: Submit after each test within 7 days.

    Full report: Submit after completion of each phase of testing within 21 days.

    785 STATIC LOAD PROOF TESTING OF WORKING PILES

    Procedure: Normal proof load test, followed by an extended proof load test to DVL + 50%

    SWL.

     Pile group designation: 500kN

    - Number of tests: 2

    Test load (maximum): DVL + 50%

    790 REQUIREMENTS FOR TEST PILES UNDER STATIC LOADING

    Construction and installation: As for working piles except as specified.

    - Exceptions: None

810 TIMING OF PILE LOAD TESTING

    Period between installation and load testing (minimum): Submit proposals.

    COMPLETION

910 HEALTH AND SAFETY FILE

    Requirement: Collate and submit a full set of pile records for inclusion in the health and

    safety file.

    Content:

    - Record drawings: With each pile numbered and giving the „as built‟ location of each pile

    relative to project grid lines.

    - Records: Copy of each record submitted during the progress of the work.

    Latest date for submission: 14 days from departure of the piling rig from site.

Author SW Bettws School Newport JOB No SC00940

    21 Dec 07 Rev -

     Page 8 of 8 clarkebond