    MOINAK ELECTRICITY TRANSMISSION PROJECT

    ENVIRONMENTAL MANAGEMENT PLAN

Background

    Implementation of the Moinak Electricity Transmission Project will provide power delivery from the Moinak Hydroelectric Power Plan (MHPP) with 300 MW capacity under construction on the Charyn River in Raimbek raion of Almaty Oblast. MHPP will reduce the deficit of electric power (especially peak power) in Southern Kazakhstan.

    The Moinak Electricity Transmission Project consists of two components construction of overhead

    transmission lines (OHTLs) and modernization/reconstruction of substations (SSs):

     reconstruction/modernization of 220 kV Shelek SS and 220 kV Robot SS and construction

    of 220/110 kV Moinak HPP Outdoor Switchyard (OSY);

     construction of 220 kV OHTL Moinak HPP 220 kV Shelek SS and 220 kV Moinak HPP

    220 kV Robot SS.

    Environment issues of construction are different for the OHTLs and SSs. Therefore, the Environmental Management Plan (EMP) consists of two parts: part I reconstruction and

    modernization of SSs and part II construction of OHTLs. Each part of EMP provides for the

    following sections:

    Section 1 project description.

    Section 2 plan of impact mitigation and pollution management.

    Section 3 monitoring requirements.

    Section 4 institutional measures for EMP implementation.

    Section 5 public consultations with affected people and stakeholders.

Section 1 Project description

    Part I Reconstruction/modernization and construction of substations

    Construction of 220/110 kV OSY at MHPP:

    The works include the construction with a configuration consisting of double main busbars and

    transfer bus with single circuit breakers. The configuration includes SF6 circuit breakers,

    disconnect switches, current and voltage transformers, and lightning overvoltage and relay

    protection systems.

    Reconstruction/modernization of 220 kV Robot SS:

    The project includes installation of the high voltage equipment in the reserve bay for 220 kV

    OHTL Moinak HPP Robot SS and replacement of high voltage equipment: circuit-breakers,

    disconnectors, current and voltage transformers, surge arresters as well as control and

    protection system.

    Reconstruction/modernization of Shelek SS:

     1

    The works include the reconstruction/modernization of the 220 kV OSY topology to “H-

    connection of transformers with the circuit-breakers incorporated in the transformer circuits

    and the repair bridge located on the side of transformers” and replacement of circuit-breakers,

    disconnectors, current and voltage transformers, and lightning overvoltage system as well as

    modernization of relay protection system.

Part II Overhead transmission lines

    This component includes construction of 220 kV OHTL Moinak HPP 220 kV Shelek SS and 220 kV

    OHTL Moinak HPP 220 kV Robot SS.

    Route of 220 kV OHTL 220 kV Moinak HPP 220 kV Shelek SS is 97 km long, and passes the

    territory of Enbekshikazakhsky raion of Almaty oblast used as grazing land.

    The route of 220 kV OHTL Moinak HPP 220 kV Robot SS is 225 km long, and passes the territory

    of Enbekshikazakhsky, Ilisky and Talgarsky raions of Almaty oblast used as grazing land. The routes of OHTL do not cross any mineral deposits and specially protected natural areas (national parks).

    To ensure safety and normal operating conditions of electrical grid and to prevent accidents the establishment of protected zone is projected for 220 kV OHTL.

    Projected OHTL routes cross Charyn River as well as numerous small rivers. Long-span towers at river crossing will be erected outside of river water protection zone.

    During construction period the main sources of environment pollution are construction mechanisms, which disturb the soil and plant cover.

    Temporary impact will be added by pollutant emissions of construction equipment exhaust. Soil and plant covering pollution might occur in places of petroleum, oil, and lubricant store places. In addition to that, environment is also affected by:

    newly constructed and extended substations with their structures and OHL towers due to land

    acquisition;

    reactors and autotransformers being the noise sources and possible subterranean waters pollution. In order to prevent destruction of fauna it is prohibited:

     to burn out vegetation, use toxic chemicals for shrubbery clearing of territories subject to

    construction of energy structures;

     to pollute soil with petroleum, oil, lubricants, and other substances dangerous for fauna and

    animals’ habitat.

    Construction of the project structures will be carried out by workers living in temporary mobile camps. Camps will be located not closer than 250 m from rivers. Wastes will be transported to special waste storage areas.

     2

Section 2: Impact Mitigation Plan

    Part I: Reconstruction/modernization of substations: 220 kV Robot SS,

    220 kV Shelek SS, construction of 220 kV OSY at Moinak HPP

    Environment Mitigation actions Mitigation Responsible Start End impact expenses

    (if material

    ones)

    During construction

    Land use on the It is planned to remove the fertile soil layer and store it in Minimal Contractor/ Senior In the After completion substation territory the isolated area under plastic cover to prevent erosion Engineer of the beginning of of construction

    and protect from surface waters. After construction is MES branch construction

    complete the fertile soil layer will be placed back to its (branch

    original location and original vegetation will be restored. Almatinskiye MES

    All vegetation will be removed mechanically or manually Branch, KEGOC

     no pesticides will be used. JSC)

    Emission of Distributed disposition of construction equipment to Insignificant Contractor/ Senior In the After completion pollutants by mitigate the impact; timely technical inspection of Engineer of the beginning of of construction construction construction equipment. MES branch construction

    equipment

    Dust The construction site will be sprinkled, especially for hot, Insignificant Contractor/ Senior In the After completion

    dry and windy conditions. Engineer of the beginning of of construction

    MES branch construction

    Audible noise Construction activities will be performed only during Insignificant Contractor/ Senior In the After completion

    normal working hours (from 8 a.m. till 6 p.m.). If Engineer of the beginning of of construction

    construction activities have to be performed before or MES branch construction

    after the specified time limits, the local society must be

    notified about it at least one week in advance.

    Accidental Find of According to the Law of the Republic of Kazakhstan No. Insignificant Contractor/Senior In the After completion Culturally 1488 dated 2 July 1992 “On protection and usage of Engineer of the beginning of of construction Significant historical and cultural heritage: the works shall be MES Branch of construction

    Artifacts suspended until found artifact is inspected by Culture KEGOC

    Committee of Culture and Information of the Republic of

    Kazakhstan and an official permission to continue works

    is issued.

     3

    Worker camps will be sited at least: Insignificant Contractor/Senior In the After completion Worker camps (a) 1 km from any protected areas (international, national, Engineer of the beginning of of construction activity raion, or oblast), MES Branch of construction

    (b) 250 m from any surface water bodies. KEGOC

    Water for the camps will be provided from local water-

    supply sources.

    Bio toilets will be used in worker camps. Wastes of the

    toilets and waste waters will be collected in special

    cesspits and pumped out as they are filled and then

    removed with special transport to the nearest sewerage

    system or sewage tanks.

    Upon completion, campsite will be restored and

    revegetated to as close to the original condition as

    possible

    Non-toxic solid To be removed to places specially allocated for landfills, Insignificant Contractor/ Senior In the After completion wastes (metal, approved by local authorities Engineer of the beginning of of construction packing and used MES branch construction equipment, etc.)

    PCB Tender documents shall prohibit procurement of Insignificant Contractor/ Senior After After all (polychlorinated equipment containing PCB Engineer of the equipment is equipment is biphenyls) MES branch delivered delivered

    During operation

    Audible noise Populated localities must be at least 800 m away from Insignificant Senior Engineer of During Continuous

    substation (Sanitary Regulations No. 1.02.007-94). the MES branch operation

    Operating personnel must be equipped with ear

    protectors.

    EMF All high voltage equipment will be wire-fenced or placed Insignificant Senior Engineer of During Continuous

    in enclosures. Max EMF intensity outside the protected the MES branch operation

    area - 5 kV/m (Standard design 13300 TM).

    For security reasons the following stationary protection

    will be used:

    ; shielding-sheds over the disconnector operating

    mechanisms,

    ; circuit breaker control cubicles,

    ; terminal boxes;

    ; shielding-sheds over walkways of routine inspection.

     4

    Prevent soil and Installation of oil collectors, made in compliance with Insignificant Senior Engineer of During Continuous ground water standard design solutions of precast concrete and the MES branch operation contamination as a reinforced concrete elements, the bottom monolith

    result of oil leak reinforced concrete slab made of sulfate-resistant cement.

    Improved damp proof shall be done underneath the slab.

    Fire prevention Grass at substation territory shall be mowed; mowed Insignificant Senior Engineer of During Continuous

    grass shall be removed from the territory of a substation. the MES branch operation

    Plants shall not be removed by pesticides.

    Solid wastes Solid wastes shall be transported to special disposal Insignificant Senior Engineer of During Continuous

    places, approved by local government authorities. the MES branch operation

     5

    Impact Mitigation Plan

    Part II: 220 kV Overhead transmission line Moinak HPP 220 kV Shelek SS,

    Mitigation actions Mitigation Responsible Start End 220 kV

    expenses Moinak HPP

     220 kV

    RobotEnviron

    ment impact

    During construction

    Land use at the It is planned to remove the fertile soil layer and store it in the Minimal Contractor/ In the After tower spots and isolated area under plastic cover to prevent erosion and protect Senior Engineer beginning of completion of along the right-from surface waters. After construction is complete the fertile of the MES construction construction

    of-way soil layer will be placed back to its original location and original branch

    vegetation will be restored. All vegetation will be removed

    mechanically or manually no pesticides will be used.

    The works on the OHTL routes passing the agricultural lands

    will be performed as approved by the land users and during the

    period when these lands are not covered with the crops or if

    these crops could be safely protected.

    Emission of Distributed disposition of construction equipment to mitigate the Insignificant Contractor/ In the After pollutants by impact; timely technical inspection of construction equipment. Senior Engineer beginning of completion of construction of the MES construction construction equipment branch

    Dust The construction site will be sprinkled were possible, especially Insignificant Contractor/ In the After

    for hot, dry and windy conditions. Senior Engineer beginning of completion of

    of the MES construction construction

    branch

    Audible noise Construction activities must be limited by normal working hours Insignificant Contractor/ In the After

    (from 8 a.m. till 6 p.m.). If construction activities have to be Senior Engineer beginning of completion of

    performed before of after the specified time limits, the local of the MES construction construction

    society must be notified about it. branch

    Non-toxic solid To be removed by Contractors to places specially allocated for Insignificant Contractor/ In the After wastes (metal, landfills, approved by municipal sanitary inspection authorities, Senior Engineer beginning of completion of packing and used or to be transported by Contractor, having license for waste of the MES construction construction equipment, etc.) disposal. branch

     6

    Quality of the Water protection zone where limited activity mode is applied Insignificant Contractor/ Prior to the After surface water at makes 100 m from rivers. Senior Engineer beginning of completion of the river (lake, Camps will be located not closer than 250 m from the edge of of the MES construction construction etc.) crossing the river or lake. No waste or waste water removal into the branch

     surface water is allowed, therefore the septic pits or dust holes

    shall be used to be serviced daily.

    Tower footing shall be located outside the sanitary bank zones of

    the rivers and lakes.

    Accidental Find According to the Law of the Republic of Kazakhstan No. 1488 Insignificant Contractor/ In beginning After of Culturally dated 2 July 1992 "On protection and usage of historical and Senior Engineer of completion of Significant cultural heritage” the works shall be suspended until found of the MES construction construction Artifacts artifact is inspected by Culture Committee of Ministry of Culture branch

    and Information of the Republic of Kazakhstan and an official

    permission to continue works is issued.

    Migratory birds The route does not cross the nesting and migration of the large

    birds

    Contractor/Senior Worker camps will be sited at least: Insignificant In the After Worker camps Engineer of the (a) 1 km from any protected areas (international, national, raion, beginning of completion of activity MES Branch of or oblast), construction construction KEGOC (b) 250 m from any surface water bodies.

    Water for the camps will be provided from local water-supply

    sources.

    Bio toilets will be used in worker camps. Wastes of the toilets

    and waste waters will be collected in special cesspits and

    pumped out as they are filled and then removed with special

    transport to the nearest sewerage system or sewage tanks.

    Upon completion, campsite will be restored and revegetated to

    as close to the original condition as possible

    During operation

    EMF The tower height is designed to make the maximum field Insignificant Senior Engineer During After

    intensity be 10 kV/m at the motorways and 1 kV/m at 30 m of the MES commissionicompletion of

    distance from the outmost conductors in the residential area branch ng of OHTL construction

    (Sanitary norms #3.01.036-97)

    Senior Engineer of Maintenance and No herbicides will be used to control vegetation along ROW. Insignificant During route Continuous

    MES Branch of checking of the Manual or mechanical methods will be used. alignment monitoring KEGOC right-of-way

    Burning to clear and control vegetation along ROW is also

    prohibited

     7

    Section 3: Monitoring plan

    Part I: Reconstruction/modernization of substations: 220 kV Robot SS,

    220 kV Shelek SS, 220 kV OSY of Moinak HPP

    Environment Monitoring Place of Monitoring Monitoring schedule MonitoriResponsible Start End impact parameter monitoring method ng

     expenses

    During construction

    Land use on the Methods and Fertile soil Visual inspection Weekly, during site InsignificContractor/ Inspection of After fertile soil substation place of storage areas preparation ant Senior site prior to removal is over territory fertile soil Engineer of fertile soil

    storage the MES removal

    branch

    Emission of Air emission Construction Calculation of During construction InsignificContractor/ The beginning The end of pollutants by permit, site and access emissions from the ant Senior of construction construction construction records and road reported quantity of Engineer of equipment payments for motor transport the MES

    local when making branch

    environmental payment of air

    bodies emission charge

    Dust Daily Construction Visual inspection During construction InsignificContractor/ The beginning The end of

    inspection site and access ant Senior of construction construction

    road Engineer of

    the MES

    branch

    Audible noise dB(А) Construction Measurements to be According to Sanitary InsignificContractor/ The beginning The end of

    site and access done under the Regulations No. ant Senior of construction construction

    road contract with 1.02.007-94 RK Engineer of

    specialized measurements shall the MES

    company holding be conducted once in branch

    license of Ministry three years, standard

    of Health of value is 80 dBA.

    Kazakhstan, and

    owing a certified

    laboratory.

     8

    Solid wastes Clarification Prior to access Visual inspection Prior to granting InsignificContractor/ The beginning The end of (metal, packing of to access to construction ant Senior of construction construction and used Contractor’s construction site Engineer of materials, etc.) license site the MES

     expiration branch

    date

    Accidental find of InsignificContractor/ The beginning The end of If find Site of Visual, interviews Immediately after culturally ant Senior of construction construction occurred, accidental with Contractor find occurred, but significant artifacts Engineer of were proper find no later than one the MES procedures day branch followed

    ; Camp ; Prior to Campsite Visual InsignificContractor/ The beginning The end of Worker camps location constructing ant Senior of construction construction activity ; Drinking campsite Engineer of

    water ; During campsite the MES

    source use branch

    ; Sewage ; During campsite

    disposal use

    system ; After

    operation construction is

    ; Camp completed

    restoratio

    n

    PCB Invoice for At delivery Visual inspection When equipment has InsignificContractor/ Arrival of Arrival of (polychlorinated equipment site been delivered ant Senior equipment equipment biphenyl) Engineer of

    the MES

    branch

    During operation

     Distance to Substation site Measurements to be According to Sanitary InsignificSenior Start of Continuous

     the nearest and nearest done under the Regulations No. ant Engineer of operation

     populated populated contract with 1.02.007-94 RK the MES

     localities locality specialized measurements shall branch

     company holding be conducted once in

    Audible noise license of Ministry three years, standard

     of Health of value is 80 dBA.

    Kazakhstan, and

    owing a certified

    laboratory.

     9

    Usage of ear Control of InsignificSenior Start of Continuous

    protectors by workers at ant Engineer of operation

    the personnel substation site the MES

    branch

    EMF EMF intensity In the area of Measurements to be Sanitary Regulations InsignificSenior Once, in the -

     operation and done under the No. 3.01.036-97** ant Engineer of beginning of

     at the fence contract with The measurement the MES operation

     specialized will be done once branch

     company holding after substation

     license of Ministry commissioning to

     of Health of verify the compliance

     Kazakhstan, and with the design

    owing a certified parameters (see table

    laboratory. below)

    Operation of the Prevent soil Over the To protect the soil, Possible leaks will be InsignificSenior Start of Continuous oil filled contamination surface and the oil extraction inspected (visually) ant Engineer of operation equipment with underneath the will be performed once a month. the MES

    transformer oil containing into the oil branch

    oil equipment collector.

    Fire prevention Formation of At substation Planning of territory As required InsignificSenior During Continuous

    intensive site clearing work ant Engineer of operation

    plant cover weed moving the MES

    branch

    Solid wastes Prevent soil At substation Planning of removal Calculation of formed InsignificSenior During Continuous

    contamination site of solid wastes wastes ant Engineer of operation

     the MES

    branch

     10