APL REEFER CONTAINER INSPECTION CRITERIA

    Section No: I- 01 Bulletin: A 2.1 Prepared by: Christopher Lee

    th thEffective: 26Nov 2001 Revision: 26 Nov 2001

SCOPE

    This guideline is applicable worldwide and described the inspection and repair criteria for the maintenance and repair of APL’s in-service reefer container.

1 INTRODUCTION

1.1 GENERAL

    ; These criteria are designed for use at all insulated reefer container inspections;

    ; Items not specifically detailed in the criteria are covered by this general introduction only if

    they require repair;

    ; The tolerances / permitted damages listed are selected to ensure the container is

    serviceable while minimising the need for repair and thereby preserving asset life; and

    ; The repair method selected should be the most economical and suit the particular repair

    location.

1.2 ACCEPTABLE DAMAGE

    This is defined as damage that is not to be repaired and includes:

    ; All flange damage except damage to weld connections;

    ; Deformation of structural members up to ISO +10mm on the side face and ISO +5mm on the

    end face; and

    ; Previous repairs should not be reworked unless the structural integrity of the container is

    compromised or it is unsuitable for cargo.

1.3 NON-ACCEPTABLE DAMAGE

    This is defined as damage that must be repaired because:

    ; The International Convention for Safe Containers, 1972, as amended (CSC) is violated and

    container safety is affected;

    ; The Customs Convention is violated;

    ; There is a reduction in the internal dimension by more than 25mm;

    ; The container is unsuitable for cargo;

    ; Cracks in welds are present unless otherwise stated; and

    ; Corrosion, which causes loss of structural integrity.

APL CONTAINER INSPECTION CRITERIA (UCIRC)

    Section No: I- 01 Bulletin: A 2.2 Prepared by: Christopher Lee

    stEffective: 16 Nov 2001 Revision: 21 Nov 2001

1.4 WEAR & TEAR

    This is defined as unavoidable change or deterioration of the condition of the container brought

    about by routine operational use and includes:

    ; General Foam deterioration such as poor insulation;

    ; Deterioration of door gaskets, fittings and hardwares;

    ; Deterioration of door fixings arising from deterioration of doors;

    ; Panels or linings delaminations resulting from routine container handling operations

    process;

    ; Deterioration of electrical, electronics components e.g. motors or PCB’s controllers

1.5 MANUFACTURING DEFECTS

    ; Manufacturing defects or suspected manufacturing defects are to be reported to APL

    Corporate M&R.

    ; Malfunction Components that are within the warranty period should to be reported to the

    respective APL office.

    APL CONTAINER INSPECTION CRITERIA (UCIRC) Section No: I- 01 Bulletin: A 2.3 Prepared by: Christopher Lee

    stEffective: 16 Nov 2001 Revision: 21 Nov 2001

2 PRIME STRUCTURAL COMPONENTS

COMPONENT DAMAGE RECOMMENDED REPAIR

    METHODS

    2.1 RAILS, HEADERS & SILLS

    Top side rail Holed, cut, torn, broken, cracked Weld or straighten, or straighten

    Deformation in excess of 27mm and weld, or insert, or section, or

    splice (Alum.), or renew

    Front & rear Holed, cut, torn, broken, cracked Weld or straighten, or straighten headers or Top Deformation in excess of 35mm (except rain and weld, or insert, or section, or end rail gutters no repair) splice (Alum.), or renew

    Aluminium top / Broken, cut, torn, cracked excess of 300mm, Weld or straighten, or straighten end rail flanges as long no leaking or cracking of roof sheets. and weld, or insert, or section, or

    No web cuts splice (Alum.), or renew

    Front & rear sill Holed, cut, torn, broken, cracked Weld or straighten, or straighten and Bottom side Deformation in excess of 50mm and weld, or insert, or section, or rail web splice (Alum.), or renew

     Flange cracked, cut or torn no repair, except Weld or straighten, or straighten cracks or tears which extend into web radius and weld, or insert, or section, or Flange splice (Alum.), or renew

    Gussets Holed, cut, torn, broken, cracked no repair No action

    Rain Gutters Holed, cut, torn, broken, cracked no repair, Straighten or remove

    except interfering with the doors operations or

    out of the corner casting face +10mm

    2.2 POSTS

    Corner posts Holed, cut, torn, broken, cracked Weld, or straighten and weld, or

     insert or renew

    Dents exceeding 25mm Straighten, or insert or renew

    Bend, bow or deformation, if exceeding outer Straighten, or insert or renew

    faces of corner castings by +5mm on end face

    or +10 mm on side face

    J- Bars Interfering with door operation and unable to Straighten, or insert or renew

    open 270º and to close fully, or any

    deformation such as bow, dent, bend, etc that

    causes the door to be impaired

    Bend, bow or deformation, if exceeding outer Straighten, or insert or renew

    faces of corner castings by +5mm on end face

    or +10 mm on side face

    Corner castings Cracked, deformed, broken Replace

    Deformation preventing correct twist lock Replace

    operation

    APL CONTAINER INSPECTION CRITERIA (UCIRC) Section No: I- 01 Bulletin: A 2.4 Prepared by: Christopher Lee

    stEffective: 16 Nov 2001 Revision: 21 Nov 2001

    COMPONENT DAMAGE RECOMMENDED REPAIR

    METHODS

    2.3 FLOOR UNDERSTRUCTURE

    Fork lift pocket Horizontal webs holed, cut, torn, or cracked in Weld, or straighten and weld, or and goose neck excess of 500mm or extending into a weld insert, or renew

    tunnel assembly, connection

    including tunnel Lower flange connection to bottom side rail, Weld, or straighten and weld, or rails, bolster, holed, cut, torn or cracked extending into web insert, or section or renew

    plate, stiffeners radius

    and forklift strap Web deformation below line of corner castings Straighten, or straighten and weld,

     face or insert, or renew

    Upper flange or plate pushed up in excess of Straighten or weld, or straighten

    50mm, cut, torn or broken and weld, or insert, or renew

    Strap broken, cracked, cut, torn, missing Weld, or straighten and weld, or

    renew

    Web holed, torn, broken, cracked, cut, missing Weld, or straighten and weld, or

     insert, or renew

    Web deformed in excess of 75mm on 3 Weld, or straighten and weld, or

    consecutive, only repair the center one insert, or renew

    Fork lift pocket, Bowed up by more than 50mm or below line of Straighten, or straighten and weld,

    outriggers and corner castings face or insert, or renew

    crossmembers Horizontal webs holed, cut, torn, or cracked in Weld, or straighten and weld, or

    excess of 500mm or extending into a weld insert, or renew

    connection

    Members Horizontal webs holed, cut, torn, or cracked in Weld, or straighten and weld, or (Aluminium type) excess of 50mm should be repaired by drilling insert, or renew

    stop hole, except no cuts at T-Clips.

    Flange cuts, tears or cracks no repair, except Weld, or straighten and weld, or

    extended to the webs radius insert, or renew

    Subfloor panels Delamination from foam insulation in excess of Repair

    over 3 square meters or affecting the structural

    integrity of the container.

    Bowed up by more than 50mm or below line of Straighten, or straighten and weld,

    corner castings face or patch, or insert, or renew

    Holed, cut, torn, broken, cracked Straighten, or straighten and weld,

    or patch, or insert, or renew

    APL CONTAINER INSPECTION CRITERIA (UCIRC) Section No: I- 01 Bulletin: A 2.5 Prepared by: Christopher Lee

    stEffective: 16 Nov 2001 Revision: 21 Nov 2001

3 OTHER COMPONENTS

    COMPONENT DAMAGE RECOMMENDED REPAIR

    METHODS

    3.1 ALUMINIUM T-FLOOR

    T-Floor and Bowed upward into the cube in excess of Straighten, section or renew

    panels 25mm

    Dents in excess of 15mm in any direction. Straighten, section or renew

    “T” bar flanges protruding upward by 5mm. Straighten, section or renew

    Delamination from foam insulation or other Repair

    damage affecting T-floor strength

    Spacing between adjacent “T” bars greater Straighten, or straighten and weld,

    than 60mm or smaller than 10mm. or section or renew

    Holed, cut, torn, broken, cracked Weld, or straighten and weld, or

    section, or renew

    Drain Plugs & Damage or missing no repair required, “unless Renew

    Chains / Kazoo / required by customer”

    Baffle Plate Ties

    Interior unit Cut, holed or cracked or fasteners missing no Weld, or straighten and weld, or Bulkhead Doors repair required, “unless affect the air flow or section, or renew

    panels required by customer”

    Return Air Grill Cut, or deformation affecting the air flow Weld, or straighten and weld, or

    section, or renew

    3.2 DOORS

    Door assembly, Holed, cut, torn, broken, cracked component or Weld or straighten, or straighten including panels, weld, or deformation affecting security and and weld, or patch, or insert, or hardwares, operation of doors renew

    hinges, locking Missing or loose parts which affect door Refit or renew bars, pins, operation or water tightness or thermal keepers tightness

    Exposure of foam Repair

    Tie back Damage or missing no repair required, “unless Renew

    required by customer”

    Exterior and Deformation such as bend, bow dent in excess Straighten, or straighten and weld, Interior door of 30mm or patch, or insert, or renew

    panels Delamination from foam insulation in excess of Repair

    1.5 square meters or affecting the structural

    integrity of the container

    Gaskets Holed, torn, cut, burned, cracked or partial Bond with Cyanoacrylate

    missing affecting water tightness or thermal adhesives are recommended, or

    tightness insert, or section, or renew

    Data plates Loose or missing plates Refasten or replace

    APL CONTAINER INSPECTION CRITERIA (UCIRC) Section No: I- 01 Bulletin: A 2.6 Prepared by: Christopher Lee

    stEffective: 16 Nov 2001 Revision: 21 Nov 2001

    COMPONENT DAMAGE RECOMMENDED REPAIR

    METHODS

    3.3 PANELS

    Exterior/Interior Deformation such as bowed, dented, bend in Straighten, or straighten and weld,

    side / front / roof excess of 40mm on the side and front inboard patch, insert or renew

    panels including corrugation panels and 50mm on roof panels

    header plate and and headers plates or cove angles

    cove angles Holed, torn or cut Weld, or straighten and weld,

    patch, or insert, or renew

    Dents exceeding the outer face of corner Straighten, or straighten and weld,

    castings +20mm or patch, or insert

    Delamination from foam insulation in excess of Repair

    over 3 square meters on both interior and

    exterior side panels, or 5 square meters on

    both interior and exterior roof panels, or

    affecting the structural integrity of the container

    If delamination from foam insulation in excess Repair

    of over 3 adjacent interior panels only or

    exterior panels only, or affecting the structural

    integrity of the container

    Interior panels dent into cube more than 25mm Straighten, or straighten and weld,

    patch, insert or renew

4 OTHER ITEMS

    COMPONENT DAMAGE RECOMMENDED REPAIR

    METHODS

    Lashing rings Broken, cracked or missing or non functional Weld, or replace, or straighten

Interior Surfaces Glue (Sticky) Clean and/or paint

    Odour, infestation, debris, contamination that Clean and/or remove

    can be transferred

    Vents blocked, loose, damaged and not Repair/replace

    weather tight, missing

    Graffiti / foreign markings - offensive / possibly Repair / remove

    offensive

    ISO decals Missing or illegible Replace

    Hazardous labels Remaining on panels Remove

    APL CONTAINER INSPECTION CRITERIA (UCIRC)

    Section No: I- 01 Bulletin: A 2.7 Prepared by: Christopher Lee

    stEffective: 16 Nov 2001 Revision: 21 Nov 2001

    5 GENERAL POINTS

    ; Container structure must conform to ISO dimension such as K-1 and K2 dimension.

    ; Dents on side and roof cannot be protruding more than 20mm outside the corner casting

    face, and underside must in line with the lower corner casting face. Forklift pocket straps

    must be ISO ? 10mm.

    ; Wear & Tear is unavoidable deterioration caused during normal operational use e.g. paint

    coating, delamination and corrosion. If any W&T items found on leased equipment, depot

    should advise the respective APL office for a possible swap program.

; Container must be water tightness and thermal tightness.

    ; Containers must conform to CSC (International Convention for Safe Containers) and TIR

    (Customs Convention).

    ; Whenever possible repairs should be done by minimum repair methods such as

    straightening, welding or riveting rather than inserting, patching, sectioning or renewing.

; Every repair must conform to the latest IICL repair criteria

    ; The minimum length of inserts or patches in any component is 150mm. There is no

    minimum distance from component ends to insert, except prime structure component must

    conform to latest IICL repair criteria.

    ; “Improper” repairs that are still structurally safe, serviceable, thermally sound and

    watertight must not be reworked. However, very obvious old and existing improper repair

    should be noted on the EIR or Repair Estimate at time of gate-in by depot.

    ; Any “Improper” repairs or “Temporary” repairs’ that are structurally unsafe, unserviceable,

    thermally unsound and not watertight must be examined and reworked to the more

    economical repair methods.

    ; Any repair not indicated by IICL or manufacturer guidelines must be referred to APL

    Regional/Corporate for further instruction.